HOME
  ABOUT CTS
  OUR PRODUCTS
  BROCHURES
  REFERENCE
  CONTACT
  UNIT CONVERTER
  LINKS
 
 

 

 

Shell France dome construction part 2: The first 3 rings

After unloading of the materials the actual dome construtcion can begin. In this case we are building the dome outside in. The advantage of this building metjod it that we are giving the dome its strength right from the start.

The first 3 rings will be built from the ground and after that we will be using cherry-pickers to make the rest of the framework.
Below you will find some pictures of the construction from ground level. This progress was made in only 3 days with 5 men.

Click on the pictures for larger format

Before we got to this point we have done quite some preparation. To get an idea of how this was executed click here

This was done during the first week. We have already moved forward in the construction. To monitor the progress click here
 

 
 
HOME | FORUM | CONTACT | SITEMAP